Notifications
Coordination alerts feed. 3 unread. The system surfaces risks; GSPE personnel decide and approve.
Protection relays not receivedHigh
PO confirmed, ETA 2026-07-14 — wiring on D001-M02-PR03 blocked.
Wiring diagram Rev A unapprovedHigh
Customer sign-off pending — 6 MV panels on production hold.
FAT readiness at risk (68%)Medium
Functional + Pre-FAT evidence missing for D001, target 2026-07-15.
Assembly Bay 1 at 90% loadMedium
Throughput bottleneck — consider night shift on Bay 2.
Container fit-out waiting on HVACMedium
HVAC unit ETA 2026-07-17 — pre-stage cabling recommended.