Node Detail
Process · Assembly & Wiring · D001-M02-PR02
Assembly
In ProgressCompletion (WIP)
50%
Planned Hours
300 h
Actual Hours
150 h
Remaining Hours
150 h
Qty Done
3/6
Progress50%
Related Shortages
| VCB-24-1250 | Vacuum Circuit Breaker 24kV 1250A | D001-M02-PR02 | 6 | 2 | 4 | Confirmed | 2026-07-09 | FAT-Critical |
Page 1 of 1
Exceptions & Recommendations
| Resource | D001-M02-PR02 | Assembly Bay 1 at 90% load | Assembly throughput bottleneck | Shift PTU fit-out to Bay 2 night shift | Production Manager | Medium |