Exceptions & Recommendations

Blocked nodes, impact propagation and recovery recommendations — each with rationale, required approval and confidence. The system recommends; GSPE personnel approve protected decisions.

5 rows
ShortageD001-M02-PR03Protection relays not received (PO confirmed, ETA 2026-07-14)Wiring blocked, FAT slips ~5 daysExpedite relay PO + resequence wiring to non-relay circuits firstPPC ManagerHigh
EngineeringD001-M02-PR03Wiring diagram Rev A not customer-approvedProduction hold on 6 MV panelsEscalate customer sign-off; release approved circuits for partial startEngineering ManagerHigh
ResourceD001-M02-PR02Assembly Bay 1 at 90% loadAssembly throughput bottleneckShift PTU fit-out to Bay 2 night shiftProduction ManagerMedium
FATD001Functional + Pre-FAT evidence missingFAT readiness 68%, target 2026-07-15 at riskLock test slot, assign QA crew after wiring completionQA/FAT OwnerMedium
ScheduleD002-M02Fit-out waiting on HVAC unit (ETA 2026-07-17)Container delivery target pressurePre-stage cabling + interior work ahead of HVAC arrivalPPC ManagerHigh
Page 1 of 1