WIP & Outstanding Work

All outstanding production, wiring and finishing jobs with remaining hours and manpower demand. Required people = remaining hours ÷ target days ÷ 8.

12 rows
D001-M01-PR02MV PanelBendingMachiningEko Saputra12030In Progress2026-07-04
D001-M01-PR03MV PanelWelding & GrindingMachiningRudi Hartono14045In Progress2026-07-07
D001-M02-PR02MV PanelAssemblyAssemblySiti Rahma300150In Progress2026-07-10
D001-M02-PR03MV PanelWiringWiringAgus Wijaya240150Blocked2026-07-12
D002-M01-PR01PTU ContainerPowder CoatingFinishingBambang S.16050In Progress2026-07-05
D002-M02PTU ContainerFit-out & WiringAssemblyDewi Lestari680330Waiting2026-07-18
D001-M01-PR01MV PanelPunching / LaserMachiningEko Saputra12010In Progress2026-07-02
D003-M01-PR01LV PanelAssemblyAssemblySiti Rahma200200Not Started2026-07-20
Page 1 of 2