Product Execution Graph

CPEG-based product execution graph: Project → Product → Module → Process. WIP is weighted by planned vs actual hours at each node.

DC-Switchgear Package — PT Nusantara PowerPRJ-001 · Project
62%
In Progress
MV Panel 24kV (x6)D001 · Product · Assembly & Wiring
63%
In Progress
Enclosure & BusbarD001-M01 · Module · Machining
75%
In Progress
Punching / LaserD001-M01-PR01 · Process · Machining
92%
In Progress
BendingD001-M01-PR02 · Process · Machining
75%
In Progress
Welding & GrindingD001-M01-PR03 · Process · Machining
68%
In Progress
Assembly & WiringD001-M02 · Module · Assembly & Wiring
56%
In Progress
PreparationD001-M02-PR01 · Process · Assembly & Wiring
89%
In Progress
AssemblyD001-M02-PR02 · Process · Assembly & Wiring
50%
In Progress
WiringD001-M02-PR03 · Process · Assembly & Wiring
38%
Blocked
PTU Container 20ft (x2)D002 · Product · Assembly & Wiring
61%
In Progress
Container ShellD002-M01 · Module · Machining
73%
In Progress
Powder CoatingD002-M01-PR01 · Process · Machining
69%
In Progress
Fit-out & WiringD002-M02 · Module · Assembly & Wiring
51%
Waiting