Node Detail
Module · Assembly & Wiring · D002-M02
Fit-out & Wiring
WaitingCompletion (WIP)
51%
Planned Hours
680 h
Actual Hours
350 h
Remaining Hours
330 h
Qty Done
0/2
Progress51%
Related Shortages
| HVAC-5KW | Container HVAC Unit 5kW | D002-M02 | 2 | 1 | 1 | Issued | 2026-07-17 | Schedule |
Page 1 of 1
Exceptions & Recommendations
| Schedule | D002-M02 | Fit-out waiting on HVAC unit (ETA 2026-07-17) | Container delivery target pressure | Pre-stage cabling + interior work ahead of HVAC arrival | PPC Manager | High |