QA & FAT Readiness

QA checkpoints and FAT readiness. Evidence-first: each checkpoint requires proof before a product can progress to FAT acceptance.

FAT target 2026-07-15
MV Panel 24kVAt Risk
68% ready7 open items
FAT target 2026-07-28
PTU Container 20ftOn Track
42% ready11 open items
FAT target 2026-08-10
LV PanelOn Track
12% ready18 open items
6 rows
D001-M01-PR03TorqueChecklistCompletePassed
D001-M02-PR03IR TestReportPartialNot StartedBlocks Pre-FAT
D001FunctionalReport + PhotoMissingNot StartedFAT date at risk
D001Pre-FATChecklist + SignatureMissingNot StartedFAT date at risk
D002-M01IncomingReportCompletePassed
D002FATReport + SignatureMissingNot StartedAwaiting wiring completion