Intent & Planning (CIGPE)

3Notifications

CIGPE — the strategic intent & planning layer: why work exists, target vs current state, gaps and the scenario plans that close them. Plans, not execution or approval.

Goals

Complete FAT before 15 August
Target 15 Aug60% · conf 72%
Reduce shortage rate below 2%
Target < 2%41% · conf 55%
Increase machine utilization to 85%
Target 85%78% · conf 80%
Reduce panel rework rate to < 1%
Target < 1%33% · conf 48%
Strategy Cascade
Enterprise ObjectiveDeliver Project Tangguh on time
Manufacturing ObjectiveShip 24 LV panels in Q3
PPC ObjectiveStage Container CTR-4471 by week 32
Production ObjectiveComplete busbar torque operation
Work OrderWO-5567
CPEG NodeEXN-9981 · Busbar Torque
Gap Analysis
Schedule gap

FAT plan 15 Aug vs forecast 21 Aug (+6 days)

Resource gap

1.5 wiremen short on Bay 3

Compliance gap

Tier III documents 80% complete

Scenario Plans — recover 6-day slip on Container CTR-4471
PlanApproachEst. CostDurationRisk
Plan AExpedite supplier (busbar)$4,200-4 daysMedium
Plan BOvertime (wiring bay)$2,800-3 daysLow
Plan CParallel production (2 bays)$6,500-5 daysHigh
Plan DAlternative component (MCCB)$1,900-2 daysMedium