Module · Assembly & Wiring · D001-M02

Assembly & Wiring

In Progress
Completion (WIP)

56%

Planned Hours

720 h

Actual Hours

400 h

Remaining Hours

320 h

Qty Done

2/6

Progress56%

Child Nodes (3)

Related Shortages

VCB-24-1250Vacuum Circuit Breaker 24kV 1250AD001-M02-PR02624Confirmed2026-07-09FAT-Critical
RELAY-7SRProtection Relay 7SR SeriesD001-M02-PR03606Confirmed2026-07-14FAT-Critical
TERM-WAGOWAGO Terminal Block SetD001-M02-PR03240120120Issued2026-07-08FAT-Critical
Page 1 of 1

QA / FAT Checkpoints

D001-M02-PR03IR TestReportPartialNot StartedBlocks Pre-FAT
Page 1 of 1

Exceptions & Recommendations

ShortageD001-M02-PR03Protection relays not received (PO confirmed, ETA 2026-07-14)Wiring blocked, FAT slips ~5 daysExpedite relay PO + resequence wiring to non-relay circuits firstPPC ManagerHigh
EngineeringD001-M02-PR03Wiring diagram Rev A not customer-approvedProduction hold on 6 MV panelsEscalate customer sign-off; release approved circuits for partial startEngineering ManagerHigh
ResourceD001-M02-PR02Assembly Bay 1 at 90% loadAssembly throughput bottleneckShift PTU fit-out to Bay 2 night shiftProduction ManagerMedium