Node Detail

3Notifications

Product · Assembly & Wiring · D002

Graph

PTU Container 20ft (x2)

In Progress
Completion (WIP)

61%

Planned Hours

1200 h

Actual Hours

730 h

Remaining Hours

470 h

Qty Done

0/2

Progress61%

Child Nodes (2)

Related Shortages

HVAC-5KWContainer HVAC Unit 5kWD002-M02211Issued2026-07-17Schedule
Page 1 of 1

QA / FAT Checkpoints

D002-M01IncomingReportCompletePassed
D002FATReport + SignatureMissingNot StartedAwaiting wiring completion
Page 1 of 1

Exceptions & Recommendations

ScheduleD002-M02Fit-out waiting on HVAC unit (ETA 2026-07-17)Container delivery target pressurePre-stage cabling + interior work ahead of HVAC arrivalPPC ManagerHigh
Page 1 of 1