Node Detail
Product · Assembly & Wiring · D002
PTU Container 20ft (x2)
In ProgressCompletion (WIP)
61%
Planned Hours
1200 h
Actual Hours
730 h
Remaining Hours
470 h
Qty Done
0/2
Progress61%
Child Nodes (2)
Related Shortages
| HVAC-5KW | Container HVAC Unit 5kW | D002-M02 | 2 | 1 | 1 | Issued | 2026-07-17 | Schedule |
Page 1 of 1
QA / FAT Checkpoints
Exceptions & Recommendations
| Schedule | D002-M02 | Fit-out waiting on HVAC unit (ETA 2026-07-17) | Container delivery target pressure | Pre-stage cabling + interior work ahead of HVAC arrival | PPC Manager | High |
Page 1 of 1